Tuesday, March 18, 2008

Footings in

Sorry for missing a day - spent the rest of the weekend fixing up the office ready for Monday.

So - today we got to go and check on progress and the fence posts for the track look great!


And the concrete was being poured for the footings while we were there.


Spoke to two, actually three people at Siemens today - to try and get them to cancel the neighbours quote request for upgrading the plinth because that is stopping us connecting! A lady called Chanti appeared to be the one stopping things so I spoke to her boss and hopefully that is sorted now! Touch wood.

We need to find a shower tomorrow and measure where the hole is for the plumber to be able to lay pipe before the concrete slab is poured - which has been delayed till Tuesday because they are booked out till Easter.

One month today till we move in!

No comments: